Shu L  - Kitchen Remodel, Bathroom remodel, Stairs Remodel

3436 El Dorado Beach Club Drive, Mercer Island

PROJECT1: KITCHEN AND 2 DOOR OPENINGS

SCOPE OF WORK

  •  Kitchen Remodel (no floor changes) , new kitchen cabinets, new countertop including island
  • Reconfigure 2 openings  up to ceiling   ( 2 doors - to the main room and from the entry ) .Drywall, plywood, or other sheathing must be removed to expose the wall framing.  Existing studs, headers, and other framing members are cut to allow for removal. 
  • Install  bottom cabinets  -   both sides of the fireplace in the living room


DOWNLOAD PLAN IN PDF

Preparation and Demolition:

Remove old  kitchen  cabinets and countertop.  Removing existing  opening framing, adjusting structural components like headers, studs, and sills. Alter the  wall to change the size of 2  existing doorway 

Rough-In, Electrical, Plumbing


Rough-In

  • Re-configure the top of the  opening  uo to ceiling, make it square. Modify the framing: The existing king and jack studs are adjusted or new ones are installed to create the desired opening size. Installing new headers.  Adjusting sills and cripples for new dimensions.


Electrical work:

No major electrical  work.

Plumbing:

As needed 

Finishing:


Kitchen Cabinet Delivery and Assembling

Kitchen Cabinets Installation


Install Kitchen Cabinets including island , adjust electrical in the island and in the tall pantry -    see the  plan


Kitchen backsplash

  • Install Kitchen backsplash  up to wall bottom cabinets on the front wall and up to ceiling and around the window on the right wall.
  • Install faucet
  •  Re-install fridge, gaz stove, dishwasher.
  •  Re-install  hood (move  it up to 6 inches)


Finishing 2 openings

 This involves  adjusting structural components like headers, studs, and sills, and installing new casing moldings for desired dimensions  to frame the opening and cover the gap between the drywall and the frame. Calk and paint.


 Paint Kitchen area  and trims: Paint kitchen area  -   walls -white, 2 coats


Total for PROJECT 1: Labor and rough materials: $9900 (before tax)

Additional for cabinets and countertop


Pre-made Kitchen Cabinets, including cabinets for living room near fireplace  (pre-made kitchen cabinets)  : $5900 / before tax

Quarts Countertop (Pearl Fantasy):  -   $3500 / before tax

Custom  Kitchen Cabinets  including cabinets for living room near fireplace from  Bellmont  (SERIES 1600) -  $14700 / before tax

* We assume that  the flooring is already installed  under the island.   If there is no floor under the island it will be a gap as the new island depth will be less then the existing

Suggested List of Material

KITCHEN

Faucet:



Sink

For a 30-33 inch base cabinet, you generally look for a sink that is 28 inches or smaller. This size provides enough space to install clips to secure the sink to the countertop, allows for the cabinetry's inherent thickness, and is the largest standard size that will fit.


Kitchen Cabinets. Pre-Made kitchen cabinets.

 Kitchen Cabinets  Door Style - slim shaker.   Custom Adjustment /panels will be need to fit the size.

  $5900


Kitchen Countertop. Manufacturing, Delivery, Installation, Sink Installation.

Kitchen Countertop. Style: Pearl Fantasy - Quartzite/Marble, Finished Size: 26” D x 110” W, Thickness: 2cm Edge: Square For the island the depth of countertop will be 36 - 40 “.

$3500


 Cabinet hardware



Tile - Backsplash

Cloé 2.5" x 8" Glossy Ceramic Tile in White    50sf -   up to  wall cabinets bottom, up to ceiling on the right wall with window.  Cloé Collection, a series of brilliant glazed ceramic wall tiles      $ 600


Inspiration Images

PROJECT2: STAIRS REMODEL

SCOPE OF WORK

A stair remodel involves upgrading the treads, risers, and railing for improved aesthetics and safety,  Key steps include removing existing elements like carpet, preparing the surfaces, installing new treads, risers, and newel posts, and finishing with paint or stain.

  • Treads and Risers These are the horizontal and vertical surfaces of each step. Replace the old old carpet with new wood and match existing floor.
  • Railing System This includes the newel posts, balusters (pickets), and handrail. Codes require the space between balusters to be less than 4 inches for safety. 
  •  Upgrades  matching the stair materials with your home's style or adding decorative elements to personalize the design. 

Preparation, Installation  and Finishing:

  1. Removal of Old Elements: This includes  removal of carpet, treads, padding, tack strips, and  old railing. 
  2. Surface Preparation: Sand and smooth the stringers and other surfaces for better adhesion. 
  3. Installation of New Components: Install new treads, risers. Installing  new railings and balusters /  Metal Stair Railings. 
  4. Finishing: Apply paint, stain, or other finishes to the installed components and touch up any other areas. 
  5. Total Stairs : 15 stairs  + The space where steps turn a different direction - landing.



Suggested Metal Railing

Total for PROJECT2: Labor, Finishing materials and rough materials: $7,250 (before tax)

PROJECT3: BATHROOM   1.  Bathroom 1  - bath tube >>>>  shower conversion  2. Bathroom 2 - replace the old shower glass enclose  (custom cut to adjust the bench)

SCOPE OF WORK

Bathroom 1: Preparation and Demolition:

Remove bath tube, glass,  tile around  bath tube  and on the left wall Responsible for debris disposal and taking protective measures for the rest of the house during the project.

Rough-In, Electrical, and Plumbing

  • Replace bath tube with the shower.
  • Shower Floor -  tiled with a small tiles , drain the same location.

Shower Niche: keep existing shower niche. Prepare the niche for tiling.

 Plumbing:

  • Install new shower system with mixer.
  • Tile shower walls and the left adjusted wall
  • Install shower glass sliding door




Bathroom 2:

Remove the old  shower enclosure, replace the old shower glass enclose  (custom cut to adjust the bench) .  replace the old shower glass enclose  (custom cut to adjust the bench)

Redo shower  floor tile grout: remove the old grout using a grout saw or oscillating tool . Clean the area to remove all dust and debris. Apply the new grout using a float, pressing it firmly into the joints. After the grout cures for the recommended time, apply a grout sealer to protect the new grout from stains and moisture

Total for PROJECT3- Labor and rough materials: $10,600 (BEFORE TAX)