Project Estimate
Client Name: Suraj
Location: Sammamish
Project1: closing door to garage, 3 bathrooms renovation, floor replacement.
Preparation and Demolition (to prepare for all projects
Preparation, Demolition, All Garbage Disposal:
Remove all tile from the floor, remove existing hardwood floor on main floor and upper floor.
Master Bathroom: - remove floor, step, remove tiles, remove old shower, toilet, vanity.
Upper Bathroom: - remove floor, tiles, vanity, remove old shower, toilet.
Main floor Bathroom: - remove floor, all tiles, vanity, old shower, toilet. - all up to studs and sub floor
Project1 Cost before tax : $6,800
Included: Preparation, Demolition, Disposal
Living Area: 3200sf,
Main Floor: 1700sf Upper Floor 1500sf
Floor Replacement Area: 2900sf
BATHROOMS
PROJECT 1. MASTER BATHROOM
1. Rough-In: Electrical & Plumbing
Electrical Work
- Review the existing electrical layout with the client.
Plumbing Work
- Install new shower system and mixer.
- Check and adjust shower drain as needed.
- Inspect existing vanity plumbing and adjust connections for the new vanity cabinet.
- Install or reinstall toilet and two faucets.
2. Finishing Work
Tiling
- Tile shower walls from floor to ceiling.
- Tile shower floor with mosaic tile.
- Tile entire bathroom floor, including the toilet area.
- Install and tile a shower niche (approx. 32" W x 16" H).
- Install custom shower glass partitions/door.
- Tile the wall around the bathtub from the top of the tub up to 24 inches.
Waterproofing & Substrate
- Use cement board or equivalent (DensShield, Schluter Kerdi-Board, or Wedi Board) for shower walls and floor substrate.
- Apply waterproofing membrane to all wet areas to ensure moisture protection.
3. Vanity Area
- Install new vanity unit.
- Install vanity-mounted faucets (to be confirmed with the client).
- Connect plumbing and secure units properly.
4. Paint & Finishes
- Demolish decorative wall features around the mirror (if applicable).
- Patch and prepare walls and ceiling for painting.
- Apply moisture-resistant paint on all surfaces.
- Install baseboards throughout the bathroom.
5. Lighting
- Install vanity wall lighting as per design.
- Add electrical outlet for LED mirror, if required.
- Install recessed lighting with a dimmer switch for adjustable ambiance.
6. Bathroom Accessories
- Install selected accessories
Project1 Cost before tax : $13,350
(Demolition /disposal is included in main demolition)
Included: Labor and Rough Materials.
Finishing Material provided by client (tile, vanity, mirrors, lighting, shower glass partition, shower sliding doors, shower hardware, shower system, faucets, etc ) before the work starts. Approx. cost: 5000$
Specifications, design, and a complete list of materials must be finalized before work begins.
PROJECT 2. UPPER BATHROOM
Rough-In, Electrical, Plumbing
Remove tiles. Remove wall with door between vanity and shower / toilet area, making open space. Leave pony wall separating shower and vanity.
Electrical work:
- Review the existing electrical layout with the client. Discuss if additional electrical outlets are needed.
Plumbing:
Shower, New shower System, Mixer, Check Shower Drain . Check existing vanity plumbing and new vanity cabinet. Made adjustment if needed. Install new toilet, 2 faucets
Finishing
Tiling
- Tile shower walls from floor to ceiling. Tile the shower floor. Ttile a shower niche (approx. 32" W x 16" H).
- Tile shower floor with mosaic tile. Tile entire bathroom floor
- Install the shower glass partitions and door (custom glass)
Shower glass door / partition – Client Custom Order or pre-made from store
2. Bathroom Floor and Walls
Flooring
- Install floor tile (24” x 24”) including toilet room
- Mosaic tile for shower floor
- Ensure proper leveling, alignment, and waterproofing at all transitions.
3. Vanity Area
Vanity Unit
- Install vanity unit - 72" , faucets. Connect plumbing and secure units properly.
4. Paint & Finishes
Paint
- Patch and prepare walls and ceiling for painting.
- Apply moisture-resistant paint on all surfaces (2 coats, painting is included)
- Install baseboards.
5. Lighting
- Install vanity wall lighting per design.
6. Bathroom Accessories
- Install selected accessories
Project 2 Cost before tax : $11,500
(Demolition /disposal is included in main demolition)
Included: Labor and Rough Materials.
Finishing Material provided by client (tile, vanity, mirrors, lighting, shower glass partition, shower sliding doors, shower hardware, shower system, faucets, etc ) before the work starts. Approx. cost: 4,200$
Specifications, design, and a complete list of materials must be finalized before work begins.
PROJECT 1. MAIN FLOOR BATHROOM
Rough-In, Electrical, Plumbing
- Tear down all to studs and subfloor
Plumbing:
Shower, New shower System, Mixer, Check Shower Drain . Made adjustment if needed. Install-reinstall toilet, vanity, 2 faucets
Finishing
Tiling
- Tile shower walls from floor to ceiling. Tile the shower floor, Tile a shower niche
- Tile shower floor with mosaic tile , Tile entire bathroom floor, Tile entire bathroom walls. Install the shower glass partitions and sliding door
2. Bathroom Floor and Walls
Flooring
- floor tile (24” x 24”), Mosaic tile for shower floor
3. Vanity Area
Vanity Unit
- Install vanity unit, faucet . Connect plumbing and secure units properly.
4. Paint & Finishes
Paint
- Prepare ceiling for painting. Apply moisture-resistant paint on all surfaces (2 coats, painting is included)
5. Lighting
- Install vanity wall lighting per design.
6. Bathroom Accessories
- Install selected accessories
Project 3 Cost before tax : $10,800
(Demolition /disposal is included in main demolition)
Included: Labor and Rough Materials.
Finishing Material provided by client (tile, vanity, mirrors, lighting, shower sliding doors, shower system, faucets, etc ) before the work starts . Approx. cost: 4000$
PROJECT 4 : FLOORING
Remove the old tile, level and prepare subfloor for flooring.
Finishing Material:
Recommended flooring: Click Lock Engineered Hardwood Flooring -White Oak
Labor
Price per SF - $5/SF, Estimated Floor Area: 2900SF
Project 4 Cost before tax $14,500 (Demolition /disposal is included in main demolition)
Price per SF - $5/SF for engineered wood floor, click and lock, Estimated Floor Area: 2900SF
Included: Labor and Rough Materials. Floor is provided by client before work begins ( price from $ 4.00/sf, $11,600 for 2900 sf. )