Project Estimate
Client Name: Olu Omotowa | New House Remodel
Location: Redmond
Project1: New Construction: Total area without garage is 4,342.7 SF. MAIN FLOOR AREA: 2,418.1 SF UPPER FLOOR AREA: 1,924.6 SF GARAGE (UNCONDITIONED): 645.2 SF TOTAL CONDITIONED AREA: 4,342.7 SF
SCOPE OF WORK
NOTES
This estimate excludes finishes and finish materials. Estimate include labor and rough material
We pulled the floor areas from your PDF plan. Below are the assumptions we used
Total (flooring area = 4,342.7 SF (from your plan).
Main floor footprint = 2,418.1 SF (used to estimate exterior perimeter).
Upper floor = 1,924.6 SF (used for ceilings / openings).
Living area with double height = 400 SF (20′ ceiling)
Geometry & quantity rules
- Main floor footprint treated approximately as a square to estimate perimeter. This gives an exterior perimeter ≈ 196.7 ft without garage and exterior wall area for two floors (10′ each) ≈ 3,933.9 SF. (without garage)
- Interior partitions estimated by rule-of-thumb: 10 linear ft of interior wall per 100 SF of conditioned area
- Double-height living area adds extra wall area equal to its perimeter × extra 10 ft of height (estimated additional wall area ≈ 800 SF).
- Ceiling area (flat coverage) = conditioned area = 4,342.7 SF (upper + main ceilings, accounting for the open-to-below living area).
- Insulation quantity taken as exterior wall area (both floors) + roof/ceiling area (main floor footprint) + Garage ≈ 12000 SF to insulate.
Scope exclusions / notes
- Total wall area (exterior both floors + interior + extra living double-height) ≈ 19000 SF.
- Ceiling area including garage ≈ 5,350 SF.
- Total drywall area including Garage (walls + ceilings) ≈ 24,000 SF.
- Insulation area including Garage (exterior walls both floors + roof/ceiling) ≈ 12,000 SF.
PROJECT 1: INSULATION, DRYWALL, JOINT FILLER, PAINTING+ MINOR TRIM WORK (garage included)
1) Insulation including Garage (exterior walls both floors + roof/ceiling ) 12000 SF (labor + rough material ($2,00 per SF = $24,000)) $48,000
2) Drywall — Hanging (boards only), area 24,000 SF, 1/2, Green board in bathrooms, Cement board inside showers (labor + rough material ) $42, 000
3) Drywall area 24,000 SF,—Level 4. Finishing (jointing, joint filler (explicit breakout), taping, multi-coat finish, sanding) $39550
A level 4 finish on drywall is a smooth, standard finish where tape is embedded in joint compound, followed by two additional coats on flat joints, one coat on interior angles, and three coats on fastener heads and accessories. It is the most common finish for residential and commercial projects.
5)
Painting (interior — walls + ceilings + minor trim work ) primer + 2 coats — walls & ceilings, labor + paint $80,450
( includes prep, primer two finish coats; trim/doors quoted separately)
Cost before tax : $210,000
Included: Labor and Rough Materials. Includes material delivery, stud shimming (wall prep), hanging, mudding, sanding, priming, painting and cleanup, project management.
This is a preliminary quantity + cost model based on the plan PDF and standard estimating rules-of-thumb. Final bids require takeoffs from full dimensioned plans and on-site review.
Project Duration: 6 weeks
PROJECT 2: HARDWOOD FLOORING (EXLUDING STAIRS)
Hardwood floor installation (bathroom areas excluded) - includes subfloor preparation, underlayment, installation. This cost includes underlayment but is separate from the price of the hard floor material
$42,000
Cost before tax : $42,000
Included: Labor and Rough Materials. This cost includes underlayment but is separate from the price of the hard floor material
This is a preliminary quantity + cost model based on the plan PDF and standard estimating rules-of-thumb. Final bids require takeoffs from full dimensioned plans and on-site review.
Project Duration: 6 weeks
PROJECT 3: BATHROOMS- 4 BATHROOMS
Master Bathroom (complete - including electrical, LED, plumbing, tiling, shower, bath tube, LED - luxury grade, per specs ) $20,000
Guest Bathroom (complete - including electrical, plumbing, tiling, shower, - per specs ) $15,000
Upper Bathroom 1 (complete - including electrical, plumbing, tiling, bath tube - per specs) $14,000
Upper Bathroom 1 (complete - including electrical, plumbing, tiling, shower - per specs) $14,000
Cost before tax : $63,000
Included: Labor and Rough Materials.
This is a preliminary quantity + cost model based on the plan PDF and standard estimating rules-of-thumb. Final bids require takeoffs from full dimensioned plans and on-site review.
Project Duration: 4 weeks
PROJECT 4: KITCHEN, PREP KITCHEN AND LIVING ROOM CABINETS INSTALLATION
Includes complete Kitchen Installation - electrical/plumbing, installing appliances, tiling backsplash $8,000
Prep Kitchen Cabinets installation - electrical/plumbing, installing appliances, tiling backsplash $2,000
Living room Cabinets installation - electrical/plumbing, installing appliances, tiling backsplash $1,500
Cost before tax : $11,500
Included: Labor and Rough Materials.
This is a preliminary quantity + cost model based on the plan PDF and standard estimating rules-of-thumb. Final bids require takeoffs from full dimensioned plans and on-site review.
Project Duration: 1 Week
TOTAL FOR 4 PROJECTS: $326,500.